Hi,
We are configuring the optimizer to generate the best fit solution.
TWO customers, ONE DC , TWO PLANTS, TWO products both assembled at one resource
We have uploaded the following data:
1. PMINLOTSIZE , PMAXLOTSIZE
2. TMINLOTSIZE, TMAXLOTSIZE
3. PRODUCTIONCOSTRATE, TRANSPORTATIONCOSTRATE
4. LEADTIMES FOR PRODUCTION, TRANSPORTATION
5. NONDELIVERYCOSTRATE
6. INVENTORYTARGET, INVENTORYTARGETVIOLATIONCOST, MAXINVENTORY
The heuristics is running correctly and generating the key figures for production as per the ratios defined.
However, the optimizer runs without errors but production is nil. Please refer to the log below:
Information | SCMPLAN | 9100 | Optimizer started |
Information | SCMPLAN | 9101 | Optimizer finished |
Information | SCMPLAN | 9102 | Optimizer found optimal solution |
Information | SCMPLAN | 9120 | Optimizer solving time: 0.01 seconds |
Information | SCMPLAN | 9121 | Optimization problem contains 3321 variables |
Information | SCMPLAN | 9122 | Optimization problem contains 1459 linear constraints |
Information | SCMPLAN | 9130 | Solution information: demand fulfillment rate is 0.00% (not delivered amount: 113799.122013) |
Information | SCMPLAN | 9131 | Solution information: objective function value is 11379999.951299995 |
Information | SCMPLAN | 9132 | Solution information: objective function bound is 11379999.951299995 (gap to found solution: 0%) |
Information | SCMPLAN | 9133 | Solution information: total non-delivery costs are 11379912.201299995 |
Information | SCMPLAN | 9143 | Solution information: total inventory target violation costs are 87.749999999999972 |
Information | SCMPLAN | 9149 | Solution information: inventory target fulfillment rate is 0% (not satisfied amount: 175500) |
Thhe Optimizer does not give a feasible solution i.e. production quantities are 0 , have i missed out on any other input KF / setting? Request guidance in this regard.
Best Regards,
Alok Joshi